Add TN as a preferred source on Google2027–2030: Organizing backup electricity by learning from Lebanon’s experience
Imed Derouiche
Expert in energy, hydrogen and digital transition
Major electricity projects are preparing for the future. A transitional program must nevertheless protect the coming summers. Tunisia could benefit from mobilizing nearby private generation, coordinated with STEG, while drawing on the economic and institutional lessons of the Lebanese experience.
Four summers cannot remain without an answer
The power cuts experienced during the summer of 2026 have placed electricity security at the heart of everyday life in Tunisia. In July, STEG announced rolling power cuts in response to strong demand in order to preserve the system. For households, shops and businesses, these interruptions immediately deteriorate living and working conditions. [1]
An estimate published on August 25, 2026, attributed to Elyes Ben Ammar, an official of the General Federation of Electricity and Gas, refers to a shortfall of around 2,000 MW during peak hours and the need for four new power plants. This figure is a trade-union estimate and should be compared with the official forecast balance. It does not represent a permanent shortfall or an annual quantity of energy. [2]
The summers from 2027 to 2030 therefore constitute a period that needs to be secured. Their difficulty will depend on the resources actually available, demand and weather conditions. The risk calls for immediate preparation rather than waiting based solely on the completion dates of major projects.
ELMED will not replace a generation strategy
The ELMED electricity interconnection with Italy is designed for 600 MW. Terna’s planning documents place it around 2030, a projected timetable that makes it necessary to provide a margin in case of delays. The imports it will enable will depend on electricity availability, prices and trading conditions. [3]
Faced with a hypothetical 2,000 MW shortfall, 600 MW would represent at most 30% of the requirement, assuming constant demand. An interconnection provides access to electricity supply; it does not, on its own, guarantee firm supply during every peak period. ELMED, new combined-cycle power plants, renewables and storage will therefore have to complement one another.
The intermediate solution must therefore have its own logic: covering identified critical hours and reducing load shedding until structural generation capacity comes online.
The World Bank describes a substitute economy
In its 2020 report, Distributed Power Generation for Lebanon: Market Assessment and Policy Pathways, the World Bank estimated that, in 2018, the commercial generator market was worth $1.1 billion, with 1.08 million customers and approximately 4 TWh sold. These figures are historical. [4]
The report distinguishes three forms of organization: private operators, resident cooperatives and municipal services. Cooperatives generally share costs, while private operators pursue commercial profitability. The report also describes customer territories and influence relationships that complicate reforms.
Its assessment links the service provided to high costs, noise, pollution and fragile governance. The World Bank envisages a transition toward distributed solar generation. It recommends pilot projects, technical and financial tools, as well as a legal framework allowing new sales models. It also highlights obstacles related to available space and electricity integration.
The scope of this report must remain clear: it analyzes Lebanon and its possible pathways. It does not recommend a Tunisian program based on diesel generators. The proposal presented here is part of our own analysis.
Turning the lessons into a Tunisian system
These findings suggest organizing the market before a spontaneous proliferation of backup solutions creates situations that are difficult to correct. The Tunisian program should define consumer rights, operators’ obligations and exit conditions from the outset.
Private ownership would not be the only option. Business or condominium-owner cooperatives could pool equipment, while local projects could address collective needs, subject to the applicable framework. Competition would focus on cost, reliability and the service actually provided.
The proposed principle is complementary generation coordinated by STEG. Emergency self-consumption, supply to third parties and injection into the grid would be treated separately, with the necessary authorizations and safeguards.
Start with equipment already in place
A national inventory of generators at industrial sites, hotels and commercial establishments would make it possible to identify an initial reserve that could be mobilized. The power indicated on a nameplate is not enough: the condition of the equipment, sustainable output under extreme heat, endurance, available fuel and the owner’s priority needs must all be verified.
A site that powers its own activity during a peak period reduces its demand on the grid. Contractual remuneration could recognize this contribution, measured against a verifiable reference consumption. Installations reserved for the safety of people would retain priority.
Supplying neighboring users or injecting electricity into the grid would require a dedicated assessment covering connection, protection against reverse voltage, power quality and responsibilities. Local grids could be authorized in suitable configurations rather than deployed without control.
Buying availability and targeting needs
If existing resources are insufficient, tenders could select temporary modular units. Purchasing and leasing would be compared based on their total cost, delivery time, reliability and residual value. Locations would be selected according to grid constraints and proximity to loads.
Contracts would distinguish capacity availability, expressed in MW, from delivered energy, expressed in MWh. They would specify call-up windows, testing, penalties and monitoring arrangements. An operator would be paid for a verifiable service.
The objective would not be to mechanically replace 2,000 MW with diesel generators. It would be to combine additional capacity, voluntary demand reduction and renewable resources to address the shortfall actually observed hour by hour.
Subsidized diesel does not produce a free kWh
Fuel compensation is part of Tunisia’s public expenditure. The Ministry of Finance publishes budgetary data on this matter. The price and access conditions for diesel for future operators must therefore be explicitly defined; their access to subsidized fuel cannot be assumed. [5]
Two accounts are necessary: that of the operator, based on its purchase price, and that of the community, including public support. An attractive sales tariff can conceal a significant budgetary cost. The justification for backup generation will depend on its full cost and the economic losses actually avoided.
Any support would be capped, traceable and limited to authorized operations. Liters consumed would be reconciled with the kWh produced. Efficiency, noise, emissions, safety and maintenance requirements would be included in contracts. Backup fuel must not become the basis for a lasting rent.
Prepare the exit from the first contract
Solar power should reduce demand on the grid during daylight hours, depending on the actual coincidence between generation and demand. Batteries could support critical hours within the limits of their power and autonomy. To compare them properly, a battery must be described in MW and MWh.
The first projects would be selected on the basis of a localized forecast balance and then tested before summer 2027. Their expansion for 2028 to 2030 would depend on the results, updated needs and permanent capacity brought into service. Contracts would provide for their termination, reduction or conversion.
Tunisia has an interest in building its power plants and interconnections while organizing an operational reserve for the next peak periods. The debate must now focus on the MW that can actually be mobilized, the hours to be covered, the cost to the community and the responsibilities of each party.
Waiting for the next heatwave to improvise would be one choice. Preparing now for transparent and temporary backup electricity would be another. Service continuity deserves a decision before summer.
References
[1] TAP, July 20, 2026, “La STEG annonce de possibles coupures tournantes d’électricité ce mardi.”
https://www.tap.info.tn/fr/Portail-Titres-de-l-actualité/20411060-la-steg-annonce-de
[2] La Presse de Tunisie, August 25, 2026, “Électricité : un déficit de 2 000 MW aux heures de pointe, le syndicat réclame quatre nouvelles centrales.”
https://www.lapresse.tn/2026/08/25/electricite-un-deficit-de-2-000-mw-aux-heures-de-pointe-le-syndicat-reclame-quatre-nouvelles-centrales/
[3] Terna, Italy–Tunisia Interconnection ELMED and Annual Report 2024.
https://www.terna.it/en/projects/projects-common-interest/italy-tunisia-interconnection-elmed
https://download.terna.it/terna/Terna_2024_Annual_Report_8dd871205a435e0.pdf
[4] World Bank / ESMAP, 2020, Distributed Power Generation for Lebanon: Market Assessment and Policy Pathways, executive summary and sections 6, 7, 9 and 10.
https://documents1.worldbank.org/curated/en/353531589865018948/pdf/Distributed-Power-Generation-for-Lebanon-Market-Assessment-and-Policy-Pathways.pdf
[5] Tunisian Ministry of Finance, Open Budget, Compensation Expenditures.
https://openbudget.finances.gov.tn/fr/compensation-expenditures/
Do you like our content?
Add TN as a preferred source on Google
What's happening in Tunisia?
Subscribe to our Youtube channel for updates.