Tunisia: El Menzah, Tunis-Carthage, Enfidha, energy… Where do the six major projects monitored by the government stand?

    Meeting on Thursday, October 8, 2026, at the Kasbah Government Palace under the chairmanship of Prime Minister Sarra Zaafrani Zenzri, the Major Projects Commission reviewed progress on six strategic projects: the reconstruction of El Menzah Olympic Stadium, the expansion of the Borj El Amri power plant, the protection of the Sidi Bou Said hillside, the rehabilitation of Bir Ali Ben Khalifa Regional Hospital, the expansion of Tunis-Carthage International Airport, and the deep-water port and logistics zone in Enfidha.

    Beyond the announcements, the key question is now whether these projects will move from procurement procedures to construction and ultimately become operational. The six projects are at different stages of development, and publicly available information does not yet provide comparable physical completion rates for each of them.

    El Menzah: Reconstruction project moves into the contract award phase

    The reconstruction of El Menzah Olympic Stadium has been monitored by the Major Projects Commission for several months.

    A memorandum of understanding had previously been signed with the Chinese side for the stadium’s complete reconstruction, while preserving its historic architectural character and modernizing its main facilities, including the playing field, stands, athletics track, electronic equipment and associated infrastructure.

    In February 2026, the Commission also approved the award of a technical assistance assignment to a multidisciplinary engineering consultancy to support the project.

    The October 8 statement marks another step forward: the Commission said it had made a decision concerning the award of the reconstruction contract to a Chinese company.

    However, the company’s name, the final contract value and the detailed construction schedule were not disclosed in the published statement.

    Borj El Amri: 600 million dinars and up to 400 MW of additional capacity

    The expansion of the Borj El Amri power plant is intended to strengthen Tunisia’s national electricity generation capacity.

    The project notably involves installing a third gas turbine with a capacity ranging from 250 to 400 MW, along with the infrastructure required to transmit the electricity generated.

    The estimated project cost stands at 600 million dinars, while the Prime Minister’s Office has announced a target of bringing the new facilities into operation during summer 2027.

    The project comes amid rising national electricity demand, which, according to figures presented to the government, is increasing by 4% to 5% annually.

    Peak electricity demand reached 6,400 MW in July 2026, compared with 5,175 MW in 2025.

    The implementation timeline is therefore a central issue. If the summer 2027 target is maintained, construction and equipment installation procedures will need to progress within a particularly tight timeframe.

    Sidi Bou Said: Decision on contract for landslide protection works

    The protection of the Sidi Bou Said hillside against landslides was also among the projects reviewed.

    During 2026, a steering committee was established to oversee the necessary studies and interventions.

    Preparatory work focused in particular on assessing the hillside’s condition and identifying urgent measures.

    The October 8 statement indicates that the Major Projects Commission made a decision concerning the award of the contract for the protection works.

    However, the final cost, construction duration and precise implementation schedule were not disclosed in the statement.

    Bir Ali Ben Khalifa: Regional hospital remains under priority government monitoring

    In Bir Ali Ben Khalifa, in the Sfax Governorate, the project concerns the rehabilitation of the regional hospital.

    The facility has been subject to public monitoring for several years.

    A 12-bed field hospital had notably been set up to maintain certain healthcare services during rehabilitation works.

    The Major Projects Commission had previously called for the necessary procedures to be accelerated to enable the hospital to become fully operational.

    The October 8 statement confirms that the project remains under government-level monitoring, but provides no updated physical completion rate, consolidated cost estimate or revised delivery date.

    Tunis-Carthage: Target of 18.5 million passengers annually

    The expansion of Tunis-Carthage International Airport is one of the largest investments among the six projects.

    The program aims to increase the airport’s annual capacity to 18.5 million passengers by 2031.

    The announced development plan includes a new terminal capable of handling approximately 11 million passengers annually, the renovation and partial expansion of the existing terminal to reach around 7 million passengers, and the upgrading of Terminal 2 to accommodate an additional 500,000 passengers.

    The estimated cost of the entire program is approximately 3 billion dinars.

    The project has been included in the 2026 investment budget of Tunisia’s Civil Aviation and Airports Authority (OACA).

    According to publicly available figures, Tunis-Carthage handles more than 7.2 million passengers annually and accounts for approximately 60% of passenger traffic across Tunisian airports.

    The targeted final capacity would therefore represent a major expansion of the country’s main aviation hub.

    Enfidha: 3,000 hectares for a port and logistics zone

    The Enfidha deep-water port and associated logistics services zone is a long-standing project that continues to be presented as one of Tunisia’s major investments with the potential to strengthen its position in Mediterranean maritime trade.

    The planned complex would cover 3,000 hectares, divided into 1,000 hectares for port facilities and 2,000 hectares for the economic and logistics zone.

    The site offers access to waters reaching 19 meters in depth.

    The updated development plan provides for an initial phase featuring a 2,000-meter container terminal, followed by a second 400-meter section, with subsequent expansion linked to the growth of port activity.

    Official documents estimate that the port and logistics complex could generate up to 52,000 direct and indirect jobs.

    The project is also intended to be connected to the country’s road, motorway and railway networks.

    The October 8 meeting confirms that the project remains part of the government’s major infrastructure monitoring program.

    The key issue going forward will be whether the administrative and procurement procedures translate into an operational construction timetable.

    Six projects at six different stages of development

    El Menzah Stadium Decision concerning the award of the reconstruction contract to a Chinese company.

    Borj El Amri An additional 250 to 400 MW of generating capacity, an estimated investment of 600 million dinars and a target of beginning operations in summer 2027.

    Sidi Bou Said Decision concerning the award of a contract for landslide protection works.

    Bir Ali Ben Khalifa Hospital rehabilitation remains under government monitoring, with no detailed physical progress rate released on October 8.

    Tunis-Carthage Target capacity of 18.5 million passengers annually and approximately 3 billion dinars in projected investment.

    Enfidha A 3,000-hectare complex, a container terminal to be developed in several phases and an announced potential of 52,000 jobs.

    Implementation will now be the real measure of progress

    The October 8 meeting marks procedural progress for El Menzah and Sidi Bou Said, while keeping four other major projects under government monitoring.

    However, the information released does not yet allow their progress to be compared on a consistent basis.

    To assess whether the announced acceleration is translating into tangible results, four indicators will be decisive for each project: the actual construction start date, the finalized contract value, the physical completion rate and the commissioning date.

    These indicators, rather than the number of meetings or announcements, will provide the basis for assessing in the coming months whether Tunisia’s major public investment projects are moving toward completion.