The general director of dams and major hydraulic works at the Ministry of Agriculture, Faiez Moslem reported that the construction work of the Saida dam in the Oued Ellil delegation in Manouba has attained a progress rate of 77%.
Moslem told the tap agency that the work, costing 164 million dinars, should be finished at the end of 2024.
He added that the two pumping stations in Douar El Bey and El Habiba and the high-voltage transformer will be completed at the end of 2025.